(a 40-year effort to establish a high-speed rail link between calgary and edmonton has also failed.)
since the late 1960s, the federal government has made or been involved in at least half-a-dozen failed attempts to create a high-frequency or high-speed rail network in the ontario-quebec corridor.
some were timed to coincide with elections, as was the case with alto, announced by justin trudeau in february 2025, a month before carney became pm and called the election.
a planned high-speed rail line with an added stop in kingston, ont.
toronto sun graphic
mark carney touts alto as nation-building project
carney touts alto as a nation-building project supported by his major projects office.
it envisions a 1,000-km long passenger rail network running electric trains travelling at 300 km/h along a dedicated dual-track corridor, cutting existing travel times in half between toronto and quebec city, a region home to 18 million canadians producing 40% of canada’s gdp.
proposed stations are toronto, peterborough, kingston, ottawa, montreal, laval, trois-rivieres and quebec city.
the estimated cost is up to $90 billion, with construction beginning in 2029 and a planned completion date 12 to 14 years later.
alto is a publicly-owned federal megaproject partnering with a conglomerate called the cadence consortium consisting of six companies – cdpq infra, atkinsréalis, sncf voyageurs, systra canada, keolis canada and air canada – chosen, the government says, through a competitive tendering process.
the federal ethics commissioner has ruled finance minister francois-philippe champagne is not in a conflict of interest because his partner, anne-marie gaudet, is vp of environment for alto.
a timeline of the alto high-speed rail project.
toronto sun graphic
more than 50,000 high-paying jobs created during construction?
the carney government says alto will boost canada’s gdp by up to $35 billion annually, creating over 50,000 high-paying jobs during the construction phase.